White Construction planned, scheduled and executed all of the heavy rigging and hoisting associated with the Fall 2012 Maintenance Turnaround at the Detroit, Michigan Refinery.  The refinery turnaround had an aggressive, 61-day schedule and was the one of the most successful in Marathon’s history.

White Construction crews worked two shifts per day, seven days a week and peaked at 140 workers working over 70,000 direct exposure hours all of which were completed safely with Zero recordable injuries.

PROJECT SCOPE OF WORK

  • Plan, schedule, coordinate and execute  all of the heavy rigging and hoisting associated with the maintenance turnaround
  • Project team lead the lift planning, scheduling and coordination effort for all of the critical lifts in the refinery
  • White Construction, Inc. provided a fleet of 75 large cranes to handle all of the hoisting and rigging of pipe and mechanical equipment for the maintenance upgrade

PROJECT DETAILS

Categories:
Client: Marathon Oil
Location: Detroit, MI
Completed: 2012

Connect

CONTACT

3900 E. White Ave P.O. Box 249, Clinton, IN 47842

(800) 355-9401

info@whiteconstruction.com

(765) 832-2075

Mon – Fri: 8:00 – 5:00

Ready to power forward your next project?