The Rail Splitter project is located Tazewell and Logan Counties, in Illinois.  The project was built upon a glacial moraine known as Union Ridge near the town of Emden.

White Construction built the project during harsh Midwest winter conditions on an accelerated schedule.  The project recorded over 190,000 man hours with zero OSHA recordable incidents.

PROJECT SCOPE OF WORK

  • Construction of all access roads
  • Modify / Upgrade existing county roads
  • Design and build all foundations
  • Design and build substation
  • Installation of collection systems
  • Turbine erection
  • Site restoration

CONSTRUCTION PHOTOS

PROJECT DETAILS

Categories:
Client: EDP Renewables
Location: Emden, IL
Megawatts: 100.5 MW
Completed: 2009