Date January 7, 2013

Wildcat Wind Farm

Client: E.ON Climate and Renewables

 

White Construction’s Role:

  • Construction of all access roads
  • Modify / Upgrade existing county roads
  • Design and build all foundations
  • Design and build substation
  • Installation of collection systems
  • Turbine erection
  • Site restoration

 

Project Highlights:

  •  The project was executed in a sequential fashion which allowed each circuit to begin power generation while the balance of the project remained under construction

Quick Facts:

Madison & Tipton counties, Indiana

200 MW

125 GE 1.6 XLE Turbines

Completed December 2012